65 - INDEPENDENT AGENCIES - REGULATORY
407
- PUBLIC UTILITIES COMMISSION
CHAPTER
381 - SELECTION OF CONSERVATION
PROGRAM SERVICE PROVIDERS
SUMMARY: This Chapter establishes the procedures governing the
selection of service providers for conservation programs. The Commission will contract with service
providers to deliver and assist with the delivery of conservation program to
T&D utility customers. Most service
providers will be selected by means of a competitive bid process conducted by
issuing Requests for Proposals or similar documents. Some service providers will be selected without a competitive bid
process, when sole-source contracting is the most efficient means to deliver
conservation programs. The chapter also
establishes the procedure to seek reconsideration of a selection decision.
§ 1 GENERAL PROVISIONS AND DEFINITIONS
A.
Scope of Rule. This rule establishes the procedures
governing the selection of service providers of conservation programs.
B.
Definitions
1.
Aggrieved
person.
“Aggrieved person” means any person who bids in response to an RFP, RFQ
or PON and who is adversely affected by the contract award decision made
pursuant to the RFP, RFQ or PON.
2.
Bid. “Bid” means a response to an RFP, RFQ or
PON.
3.
Bidder. “Bidder” means a person or entity that
submits a bid.
4.
Commission. “Commission” means the Maine Public
Utilities Commission
5.
Conservation
Program. “Conservation programs” means programs developed by the
commission pursuant to 35-A M.R.S.A. §3211-A designed to reduce inefficient
electricity use.
6.
Contract
Administrator. “Contract Administrator” means the employee of the Commission
designated to administer contracts between the Commission and service providers
and other vendors and consultants.
7.
Program Fund. “Program fund” means the conservation
program fund established by the commission pursuant to 35-A M.R.S.A. §
3211-A(5).
8.
Program
Opportunity Notice. “Program Opportunity Notice” means a
document identifying the area or market sector of interest and the energy
efficiency goals sought to be achieved.
The document will solicit proposals on how the efficiency goals can be
achieved. As a result of the Program
Opportunity Notice, the Commission may choose one or more service providers to
work on one or more projects. This
document is also known by the initials “PON.”
9.
Proposal. “Proposal” has the same meaning herein as
the term “bid.”
10.
Request for
Proposal. “Request for Proposal” means a document listing the scope of work
for the service needed, other requirements of the Commission, and the technical
and cost evaluation criteria for selection of the service provider. This document is also known by the initials
“RFP.”
11.
Request for
Qualifications. “Request for Qualifications” means a
document listing the scope of work for the service needed, other requirements
of the Commission, and the technical evaluation criteria for selection of the
service provider. The document normally
requires only a technical response. The
Commission may select one or more service providers in response to a Request
for Qualifications and then request cost proposals, or negotiate the cost terms
of agreement with the qualified bidder(s).
The document is also know by the initials “RFQ.”
12.
Service
Provider. “Service provider” means a public or private provider of energy
conservation services or an entity selected by the Commission to contract with
such providers or otherwise arrange the delivery of conservation programs. “Service provider” also includes entities
that indirectly deliver energy conservation services to customers, such as
entities that process and pay coupons, and entities that provide assistance in
performing program evaluations.
§ 2 COMPETITIVE
PROCUREMENT
A. Competitive Bidding Process. Except as provided in Section 3, the
Commission shall select service providers through a competitive bidding
process. Competitive bidding processes
shall be conducted by issuance of one of the following documents:
1. Request
for Proposals (RFP)
2. Request
for Qualifications (RFQ)
3. Program
Opportunity Notices (PON)
The processes
shall be designed to maximize participation from qualified bidders.
B. Development of RFPs/RFQs/PONs. When the Commission is to select a service
provider by competitive bid, it shall develop and issue an RFP, RFQ, or
PON.
1.
Each RFP and RFQ will contain
sufficient information to permit bidders to develop responsive proposals. This information will include, at a minimum:
1. A
description of the scope of work required;
2. The
required content and format of the bids;
3. A list of the bid evaluation criteria
and scoring weights to be applied;
4. The date, time and place that the
proposal is due. Open solicitations may
alternately specify a notice period for closing the solicitation;
5. The name, address, and contact
information for the Commission contact person; and
6. A copy of
the standard form agreement.
In each RFP or
RFQ, the Commission will establish reasonable timeframes for the submission of
bids, the evaluation of bids, and the selection of the winning bidders.
2. Each PON will be a formal request
for projects that require responders to detail their own approach to the PON’s
topic. A PON will describe the
objectives of the program but the responder is then responsible for providing a
detailed statement of work that represents a solution to the problem outlined
in the PON. More than one contract may
be awarded as a result of the PON.
Cost-sharing by the contractor may be required.
C. Notice of RFPs, RFQs and PONs. The Administration Division will maintain a
service list of persons who will be notified whenever the Commission issues a
RFP, RFQ or PON related to a conservation program. The Commission will reasonably advertise each RFP, RFQ and
PON. Each RFP, RFQ or PON will be
forwarded to the Division of Purchases and posted on the Commission or
Efficiency Maine website.
D. Written
Questions and Pre-Bid Conferences.
The RFP, RFQ, or PON will specify the manner in which written questions
may be asked. Answers to questions will
be posted on the Commission website.
The Commission at its option may hold a pre-bid conference. Answers to all questions raised at a pre-bid
conference will be posted on the Commission website.
E. Submission
of Bids. To the extent practicable,
the Commission will accept bids electronically in response to RFPs, RFQs, or
PONs. All timely submitted bids will be
turned over to the Commission Contract Administrator. The Commission Contract Administrator shall keep a written record
of the bidder’s names, the date and time the bid was received, the cost/price
of the bid and the bidder’s contact person.
The written record kept by the Commission Contract Administrator shall
be a public document as defined in 1 M.R.S.A. § 401. The bids received in response to a RFP, RFQ or PON shall be
treated as confidential and not subject to public disclosure from the date of
submission until notification of the contract award by the Commission’s
Contract Administrator. After the
notification of the contract award, the bids become public documents.
F. Rejection
of Noncompliant or Untimely Bids; Rejection of All Bids. The Commission shall reject all bids that do
not comply with the requirements of this Chapter or the RFP, RFQ or PON, or
that are not submitted before the deadline for submitting bids established
pursuant to subsection B of this section.
The Commission may reject all bids if it finds that the bids are
unreasonably high in cost or that acceptance of any bid will not be in the
public interest.
G. Evaluation
and Selection.
1. Proposal Review Team. Responses to each RFP, RFQ and PON will be
reviewed and evaluated by an assigned Proposal Review Team. Each Proposal Review Team shall be comprised
of a minimum of three persons. The
chairperson of each Proposal Review Team shall be the Commission’s Director of
Energy Efficiency Programs, or the Director’s designee. The chairperson of each Proposal Review Team
will select the other members of the Proposal Review Team. The other members may be members of the
Commission staff or other persons who have training or experience relevant to
the conservation program for which the competitive bidding process is held.
2. Criteria. Evaluation and selection criteria will be
listed in each RFP, RFQ or PON.
Criteria shall include:
a. Cost.
b. If practicable, the extent to which
the proposal promotes the development of resources, infrastructure and skills
within the State.
c. Experience and qualifications.
d. Responsiveness to the solicitation.
e. Other qualifications as the Director
of Energy Efficiency Programs may determine.
3. Bid Review. Each member of the Proposal Review Team will
individually review all bids based on the criteria established in the RFP, RFQ
or PON. The Proposal Review Team will
document the scoring, and the substantive information that supports the
scoring, and select the winning bidder(s).
4. Review Process. The Proposal Review Team may take any of the
following steps, either with respect to all of the bids received, or to a
subset of bids selected as superior to the others:
a.
Consult with prior clients on the
performance of firms or particular persons proposed for the conservation
program.
b.
Schedule presentations or
interviews with representatives of the firms or persons proposed for the
conservation program.
c.
Conduct a review of past performance,
including a review of reports, analyses, or other materials that would reflect
on the bidder’s performance.
d.
Request additional data or
material to support bids from any or all bidders.
5. Bidder Discussions. The Proposal Review Team may review bids and
award a contract based on the bids received without discussion with any
bidders, or may conduct limited discussions or negotiations with all bidders or
a selected subset of bidders determined to have presented superior bids. The Proposal Review Team may review and
score bids after any amendments to the bids as a result of the discussions or
negotiations. The Proposal Review Team
may enter into price negotiations for a “best and final offer” with selected
bidders, prior to contract award.
6. Contract Award. The Proposal Review Team may make one or more contract awards to fulfill the requirements of the RFP, RFQ or PON. The contract award will be made to the highest rated proposal(s) that conforms to the requirements of the RFP, RFQ or PON.
7. Bid Rejection. The Proposal Review Team may summarily reject any bid it finds that contains false or misleading material information. The Commission Contract Administrator may bar any entity that has submitted false or misleading material information from participating in any contract award for a period of up to three years.
8. Notification. The Commission shall notify all bidders responding to an RFP, RFQ or PON of the contract award decision in writing, postmarked or electronically mailed a minimum of 14 calendar days prior to contract effective date. This notice will include a statement that the award is conditional pending contract review.
9. Contract Execution. After 14 calendar days from the contract award notification, the Director of Energy Efficiency Programs, or his/her designee, shall execute a written contract with the winning bidder or bidders.
10. Final Approval. Standard agreements, as described in section 4, between the Commission and selected service providers shall be sent to the State Contract Review Committee for final approval, at least seven days prior to the proposed contract effective date.
11. Effective Date. The effective date of the standard agreement shall be the date the Contract Review Committee approves the agreement.
The authority to develop and issue RFPs, RFQs and PONs, and to otherwise administer the RFP, RFQ, and PONs processes as described in this section 2, is delegated to the Director of Energy Efficiency Programs.
§ 3 OTHER TYPES OF SOLICITATIONS
The Commission may select a service provider for one or more conservation programs without employing a competitive bidding process if the Commission finds that the selection of the service provider by another solicitation process will promote the efficient and effective delivery of conservation programs and is consistent with the objectives and overall strategy of the conservation programs. Solicitations that do not employ competitive bidding processes may include:
A. Open Solicitations. An open solicitation seeks to acquire multiple service providers for a program through an on-going solicitation process. The solicitation specifies the qualifications and requirements the service provider is required to meet. Service providers meeting these qualifications must complete a cooperative agreement with the Commission to provide the specified services.
B. Sole Source Procurements. The Commission may use a sole source procurement when: 1) the service provider has unique qualifications, resources, or experience; 2) there is not enough time to use a competitive bidding process or 3) the Commission finds that the conservation program would clearly benefit from a sole source procurement. The decision whether to use a sole source procurement for $10,000 or less is delegated to the Director of Energy Efficiency Programs. The decision to use a sole source procurement for more than $10,000 will made by the Commission, or may be delegated on case-by-case basis by the Commission.
C. Low-Income Service Providers. For the delivery of conservation programs to
low-income residential customers, the Commission may, without employing a
competitive bidding process, use the delivery system of the Low Income
Weatherization Assistance for Low-Income Persons Program administered through
the United States Department of Energy, and the network of for-profit and
not-for-profit entities which have held contracts with transmission and
distribution utilities to deliver efficiency services to low-income and residential
customers.
§ 4 TYPES OF AGREEMENTS
A. Standard Agreement. Except as allowed in subsections B through E, contracts between service providers and the Commission must be in writing and use the State of Maine Agreement for Special Services form as prepared by the Department of Administrative and Financial Services, Division of Purchases. The completed standard form agreement must describe the service to be performed, the terms and conditions agreed to by the parties, the cost of the service and how payment will be made.
B. Memorandum of Understanding (MOU). The Commission may use an MOU as an alternative to the standard form agreement when implementing agreements with other government agencies.
C. Cooperative Program Agreement. The Commission may use a program agreement
as an alternative to the standard form agreement when implementing agreements
with multiple service providers under an open solicitation for a program.
D. Cooperative Agreements. The Commission may use a cooperative agreement, when implementing agreements with the University of Maine or the Maine Community College System.
E. Grant Agreement. The Commission may use a grant agreement when awarding a grant to a group, organization or other recipient. The grant agreement must describe the terms and conditions and scope of performance or action which is expected of the recipient.
§ 5 APPEALS OF CONTRACT AWARD DECISIONS
A. Request for Reconsideration. An aggrieved person may request reconsideration of a contract award decision by filing a written petition to reconsider to the Administrative Director within 14 days of the notification of the contract award pursuant to Section 2 (G)(8).
B. Petition. Each petition to reconsider must contain the award decision being appealed, the name of the aggrieved party, the facts that make the petitioner an aggrieved person and reason that the contract award decision should be reversed.
C. Review of Petition; Burden. The Commission will review and decide all petitions to reconsider contract award decisions. A petition to reconsider will be denied unless the petitioner persuades the Commission that in making the contract award decision, the Proposal Review Team:
1. committed a violation of law;
2. committed irregularities resulting in fundamental unfairness; or
3. acted in an arbitrary or capricious manner.
The petitioner has the burden of demonstrating that reconsideration should be granted.
D. Nonadjudicatory. Each petition to reconsider a contract award decision is a non-adjudicatory proceeding, as defined in chapter 110 of the Commission Rules, and shall be assigned a separate docket number. The Commission may appoint a presiding officer to assist with the orderly processing of the petition. The Commission or presiding officer may consolidate all petitions to reconsider that relate to a single contract award decision.
E. The Commission or presiding officer on its own motion or at the request of the petitioner may require additional written argument, hold an oral argument, or hold a hearing on the petition. The presiding officer shall invite a representative of the contract award winning bidder to participate in any review of a contract award.
F. Final Action. A denial by the Commission of a petition to reconsider a contract award decision constitutes final agency action.
G. Reversal. If the Commission finds that the petition has made the demonstration required by subsection B, then the contract award decision shall be reversed. The Commission may then alternatively: 1) remand the matter to the original or a newly-constituted Proposal Review Team to review the bids and award a contract consistent with the written decision of the Commission or 2) decide to issue a new RFP, RFQ or PON and begin a new selection process or 3) decide not to proceed with the conservation program.
§ 6 WAIVER OR EXEMPTION
Upon the request of any person subject to the provisions of this Chapter or upon its own motion, the Commission may waive any of the requirements of this Chapter that are not required by statute. Where good cause exists, the Commission or its designee may grant the requested waiver, provided that the granting of the waiver would not be inconsistent with the purposes of this Chapter and of Title 35-A.
BASIS STATEMENT: The factual and policy basis for this Chapter is set forth in the Commission’s Notice of Rulemaking, Docket No. 2003-517 issued on July 28, 2003. Copies of this Notice of Rulemaking have been filed with this Chapter at the Office of the Secretary of State. Copies may also be obtained from the Administrator Director, Public Utilities Commission, 242 State Street, 18 State House Station, Augusta, Maine 04333-0018.
AUTHORITY: 35-A M.R.S.A. §§ 3211-A and 111
EFFECTIVE DATE: This Chapter was approved as to form and legality by the Attorney General on _______________________. It was filed with the Secretary of State of _________________________ and will be effective on ___________________.