STATE
OF MAINE
PUBLIC UTILITIES COMMISSION Docket No. 2002-161
June
17, 2003
PUBLIC UTILITIES COMMISSION
Interim Electric Energy
Conservation
Programs
ORDER TERMINATING TWO
EXISTING T & D SPONSORED
CONSERVATION PROGRAMS
WELCH, Chairman; NUGENT and DIAMOND, Commissioners
________________________________________________________________
By this Order, we terminate Central
Maine Power Company’s (CMP) conservation program known as the Nickel Program
and Bangor Hydro-Electric Company’s (BHE) Commercial Lighting Incentive Program
(CLIP), because these programs overlap with the Commission-sponsored,
Efficiency Maine Small Business Program.
CMP may continue to fulfill contracts approved through July 1, 2003, as
long as the conservation measures are installed by December 31, 2003.
II. BACKGROUND
By order on April 8, 2002 in this docket, we established existing
utility-sponsored energy conservation programs as interim programs pursuant to
the newly-enacted Conservation Act, P.L. 2001, ch. 624, § 4. We ordered T&D utilities to:
continue to operate their existing energy
conservation programs in a manner that is consistent with recent program
operations until such time as they are directed to do otherwise by the
Commission.
April
8 Order at 2.
Accordingly, CMP continues to
operate its Commercial and Industrial (C&I) Efficiency Incentive Program,
known as the Nickel Program.[1] The Nickel Program is targeted at customers
whose electric demand is below 1000 kW.
The program is delivered by means of a standard form contract executed
with a customer (sometimes with the assistance of a vendor). If the conservation measure and customer
meet the program criteria, CMP preapproves the contract and the customer is
paid the program benefit after the measure is installed or implemented. Thus, the program is operated so that there
always will be a lag between the time a contract is approved and a conservation
measure is installed. Because CMP was
concerned that the program might be terminated after contracts were approved
but before measures were implemented, we advised CMP that it was authorized to
complete performance of contracts that were executed and approved, even though
performance might not be completed until after the Nickel Program was
terminated. Advisory Opinion
Regarding CMP’s Existing Conservation Programs, Docket No. 2002-161 (July
8, 2002).
BHE continues to operate its
Commercial Lighting Incentive Program (CLIP), targeted at commercial and
industrial customers. The program
provides incentives on a limited number of specific lighting products. The BHE program has seen little recent
activity. Only 22 units were installed
in 2002.
By Orders on June 13, 2002 and
September 24, 2002, the Commission implemented an interim Small Business
Program. Our program combines customer
incentives with an education and information effort designed to overcome the
barriers faced by small business customers.
The program is delivered by an implementation contractor through a
network of cooperating program allies, recruited from Maine contractors and
suppliers. The Commission chose L.K.
Goldfarb as its implementation contractor for the Efficiency Maine Small
Business Program, [2] which
formally began on April 15, 2003.
III. DECISION
Most of the small business customers that are eligible for CMP’s Nickel
Program are eligible for Efficiency Maine’s Small Business Program. Although both programs contain terms and
conditions that disqualify projects from the program if the measure has been
funded under another ratepayer-funded program, enforcement of these provisions
may prove difficult. Each of the
programs is administered by different entities. Unless there is adequate coordination between the Efficiency
Maine Small Business Program contractor and CMP, it is possible that ratepayers
could fund the same project twice.
To significantly reduce the
possibility of such “double funding” without incurring the administrative
burden of coordinating the Small Business Program with CMP’s program, we decide
to terminate CMP’s Nickel Program, effective on July 1, 2003. After July 1, CMP should refer all Nickel
Program-eligible customers to the Efficiency Maine Small Business Program. Consistent with our earlier Advisory
Opinion, CMP is authorized to complete performance of contracts that were
executed and approved by July 1, 2003, as long as the project is completed by
December 31, 2003.
All of the products eligible for
BHE’s CLIP eligible customer group are eligible for an incentive under
Efficiency Maine’s Small Business Program.
Thus, the potential also exists for “double funding” of lighting
products through the BHE and Efficiency Maine programs. As the program offered by BHE is covered by
the Efficiency Maine program, we decide to terminate the BHE CLIP program. BHE should refer all CLIP-eligible customers
to the Efficiency Maine Small Business Program.
Accordingly, CMP is ordered to
terminate its C&I Energy Efficiency Program (Nickel Program) in the manner
described in this Order, and BHE is ordered to terminate its Commercial
Lighting Incentive Program (CLIP).
Dated at Augusta, Maine,
this 17th day of June, 2003.
BY ORDER OF THE COMMISSION
_______________________________
Dennis L. Keschl
Administrative Director
COMMISSIONERS
VOTING FOR: Welch
Nugent
Diamond
NOTICE OF RIGHTS TO
REVIEW OR APPEAL
5
M.R.S.A. § 9061 requires the Public Utilities Commission to give each party to
an adjudicatory proceeding written notice of the party's rights to review or
appeal of its decision made at the conclusion of the adjudicatory
proceeding. The methods of review or
appeal of PUC decisions at the conclusion of an adjudicatory proceeding are as
follows:
1. Reconsideration
of the Commission's Order may be requested under Section 1004 of the
Commission's Rules of Practice and Procedure (65-407 C.M.R.110) within 20 days
of the date of the Order by filing a petition with the Commission stating the
grounds upon which reconsideration is sought.
2. Appeal
of a final decision of the Commission may be taken to the Law Court by
filing, within 21 days of the date of the Order, a Notice of Appeal with
the Administrative Director of the Commission, pursuant to 35-A M.R.S.A. §
1320(1)-(4) and the Maine Rules of Appellate Procedure.
3. Additional
court review of constitutional issues or issues involving the justness or
reasonableness of rates may be had by the filing of an appeal with the Law
Court, pursuant to 35-A M.R.S.A. § 1320(5).
Note: The
attachment of this Notice to a document does not indicate the Commission's view
that the particular document may be subject to review or appeal. Similarly, the failure of the Commission to
attach a copy of this Notice to a document does not indicate the Commission's
view that the document is not subject to review or appeal.
[1] The name was derived from the fact that a
customer could save 5¢/kWh in the first year of a project.
[2]
Efficiency Maine is the trademarked term that the Commission has adopted to
describe its statewide effort to promote the more efficient use of electricity
and otherwise fulfill its obligation under the Conservation Act.